← Previous Page
Supreme Court Extends Arbitration Timeline: Section 29A Explained

Supreme Court Extends Arbitration Timeline: Section 29A Explained

By: Adv Syed Yousuf
Share on:

The Supreme Court of India clarifies Section 29A of the Arbitration and Conciliation Act 1996. Learn about extension of time for arbitral awards, sufficient cause, and COVID-19's impact on legal timelines.

This case before the Supreme Court of India centered on the question of whether an application for extending the time for an arbitral tribunal to issue its award could be entertained if filed after the tribunal's mandate had expired. The Court also examined whether the facts of this particular case justified such an extension.

Background: The appellant, M/s Ajay Protech Pvt. Ltd. had entered into a works contract with the first respondent herein, represented by its General Manager. Disputes arose. The appellant invoked arbitration. The High Court appointed a sole arbitrator. The arbitral proceedings commenced.

Statutory Time Limits and the Impact of the Pandemic : The amended Arbitration and Conciliation Act, 1996, stipulates time limits within which an arbitral award is to be given. According to Section 29A(1) of the Act, the award has to be made within 12 months from the date pleadings are closed, with a provision allowing the parties to agree to an extension of six months under Section 29A(3).

In the present case, the pleadings were closed on October 9, 2019. The litigation then faced extraordinary interruptions caused by the COVID-19 pandemic. Thereafter, the Supreme Court took note of the deleterious impact of the pandemic on the legal lifeline and passed an order in In re: Cognizance for Extension of Limitation extending the period of limitation under various laws, including the Arbitration and Conciliation Act, from March 15, 2020, to February 28, 2022.

High Court's Order and the Appeal: The pandemic extension and, subsequently, an agreement by the parties for an extension of time having been granted, the appellant's application under Section 29A(4) of the Act was filed in August 2023. Having thus been filed more than two years after the tribunal's mandate had expired, the High Court dismissed it holding that the application was not maintainable.

Supreme Court's Interpretation of Section 29A(4):

The Supreme Court set aside the High Court order. The Court examined the language of Section 29A(4), which provides that the mandate of the arbitral tribunal stands terminated in case of failure to make the award within the time "unless the Court has, either prior to or after the expiry of the period so specified, extended the period." The Court interpreted this as expressly permitting an extension even after the expiry of the tribunal's mandate. The Supreme Court explained that the automatic lifting of the mandate provided under Section 29A(4) operates only when there is a failure to file an extension application. The Apex Court thus relied on its recent order in Rohan Builders (India) Pvt. Ltd. v. Berger Paints India Ltd., where for similar reasons, it had "allowed an application for extension of time although the initial or extended period as provided under the Act had expired."

Sufficient Cause for Extension: The Court proceeded to consider whether there was sufficient cause for the extension, in this case. It took into consideration the fact of the pandemic, exclusion of time as allowed by its earlier order in In re: Cognizance for Extension of Limitation, and the consent by parties to file such an extension.

The Court then noticed that the period from March 15, 2020, to February 28, 2022, must be excluded in calculating the delay. Thus, the appellant would have been within the time limit if the application were filed no later than March 31, 2023. However, the application was filed in August of 2023, which means it was about four months late.

The appellant accounted for this delay, owing it to various causes such as the transition to online hearings, the complexity in the dispute, and changes in the respondent's legal representation.

In the light of these considerations, the Court held that sufficient cause existed for justifying the extension of time in making the award. The Court pointed out the necessity of facilitating efficient dispute resolution through arbitration. It remarked that statutory time limits imposed by Section 29A are not absolute and that courts have discretion to extend them when justified by the circumstances.

The Court therefore interpreted that the ambit of Section 29A(4) of the Arbitration and Conciliation Act, 1996, holds that an application seeking an extension of time for making an arbitral award can be filed even beyond the efflux of the mandate of the tribunal. The judgment also highlights the applicability of exceptional circumstances, such as a COVID-19 pandemic, to determine delays in arbitral proceedings.

The Supreme Court consequently granted the appeal by setting aside the impugned order of the High Court. Grant of extension was given by the Court to the arbitral tribunal for making the award on or before December 31, 2024.

The decision of the Court further reiterated balancing the statutory timelines with the ultimate objective of ensuring fair dispute resolution via arbitration.

Coram: Justice Pamidighantam Sri Narasimha, & Justice Sandeep Mehta.
Between:MS Ajay Protech Pvt. Ltd Vs General Manager & Anr
Date of Judgment: 22-11-2024

Comments

Visitor No. 387409